Task |
Date |
Responsibility |
Project start |
15/12/98 |
All |
Network Group Meeting |
TBD |
NG |
Agree structure of D1 |
16/12/98 |
JC/HH |
Draft of D1 |
13/1 |
JC |
Submission of D1 to UKERNA |
20/1 |
JC |
Agree structure of D2 |
20/1 |
JC/HH |
Draft of D2 |
5/2 |
JC |
Submission of D2 to UKERNA |
17/2 |
JC |
Agree structure of D3, all parts |
14/4 |
DAP/HH |
Draft of D3 part1 |
5/5 |
DAP |
Submit D3 part1 to UCL |
10/5 |
DAP |
Draft of D3 part2 |
12/5 |
DAP |
Submit D3 part2 to UCL |
17/5 |
DAP |
Draft of D3 part3 |
19/5 |
DAP |
Submit D3 part3 to UCL |
24/5 |
DAP |
Submission of D3 to UKERNA |
26/5 |
JC |
Agree structure of D4 |
26/5 |
RH-J/HH |
Draft of D4 |
16/6 |
RH-J |
Submit D4 to UCL |
25/6 |
RH-J |
Submission of D4 to UKERNA |
30/6 |
JC |
Agree structure of D5 |
30/6 |
CSP/HH |
Draft of D5 |
21/7 |
CSP |
Submission of D5 to UKERNA |
28/7 |
CSP/JC |
Agree structure of D6 |
18/8 |
JM/HH |
Agree structure of D7 |
23/8 |
JC/MAS/HH |
Draft of D6 |
8/9 |
JM |
Draft of D7 |
15/9 |
JC/MAS |
Submit D6 to UCL |
15/9 |
JM |
Submission of D6 to UKERNA |
22/9 |
JC |
Submission of D7 to UKERNA |
27/9 |
JC/MAS |
Project completion |
30/10 |
All |